Formwork is an ancillary construction, used as a mould for a structure. Into this mould, fresh concrete is placed only to harden subsequently. The construction of formwork takes time and involves expenditure upto 20 to 25% of the cost of the structure or even more. Design of these temporary structures are made to economic expenditure. The operation of removing the formwork is known as stripping. Stripped formwork can be reused. Reusable forms are known as panel forms and non-usable are called stationary forms.
Timber is the most common material used for formwork. The disadvantage with timber formwork is that it will warp, swell and shrink. Application of water impermeable cost to the surface of wood mitigates these defects.
A good formwork should satisfy the following requirements:
- It should be strong enough to withstand all types of dead and live loads.
- It should be rigidly constructed and efficiently propped and braced both horizontally and vertically, so as to retain its shape.
- The joints in the formwork should be tight against leakage of cement grout.
- Construction of formwork should permit removal of various parts in desired sequences without damage to the concrete.
- The material of the formwork should be cheap, easily available and should be suitable for reuse.
- The formwork should be set accurately to the desired line and levels should have plane surface.
- It should be as light as possible.
- The material of the formwork should not warp or get distorted when exposed to the elements.
- It should rest on firm base.
Economy in Formwork
The following points are to be kept in view to effect economy in the cost of formwork:
- The plan of the building should imply minimum number of variations in the size of rooms, floor area etc. so as to permit reuse of the formwork repeatedly.
- Design should be perfect to use slender sections only in a most economical way.
- Minimum sawing and cutting of wooden pieces should be made to enable reuse of the material a number of times. The quantity of surface finish depends on the quality of the formwork.
Formwork can be made out of timber, plywood, steel, precast concrete or fibre glass used separately or in combination. Steel forms are used in situation where large numbers of re-use of the same forms are necessary. For small works, timber formwork proves useful. Fibre glass made of pre-cast concrete and aluminium are used in cast-in-situ construction such as slabs or members involving curved surfaces.
Timber Formwork:
Timber for formwork should satisfy the following requirement:
It should be
- well seasoned
- light in weight
- easily workable with nails without splitting
- free from loose knots
Timber used for shuttering for exposed concrete work should have smooth and even surface on all faces which come in contact with concrete.
Normal sizes of members for timber formwork:
Sheeting for slabs, beam, column side and beam bottom
| 25 mm to 40mm thick
|
Joints, ledges
| 50 x 70 mm to 50 x 150 mm |
Posts
| 75 x 100mm to 100 x 100 mm |
Plywood Formwork
Resin bonded plywood sheets are attached to timber frames to make up panels of required sizes. The cost of plywood formwork compares favourably with that of timber shuttering and it may even prove cheaper in certain cases in view of the following considerations:
- It is possible to have smooth finish in which case on cost in surface finishing is there.
- By use of large size panels it is possible to effect saving in the labour cost of fixing and dismantling.
- Number of reuses are more as compared with timber shuttering. For estimation purpose, number of reuses can be taken as 20 to 25.
Steel Formwork
This consist of panels fabricated out of thin steel plates stiffened along the edges by small steel angles. The panel units can be held together through the use of suitable clamps or bolts and nuts. The panels can be fabricated in large number in any desired modular shape or size. Steel forms are largely used in large projects or in situation where large number reuses of the shuttering is possible. This type of shuttering is considered most suitable for circular or curved structures.
Steel forms compared with timber formwork:
- Steel forms are stronger, durable and have longer life than timber formwork and their reuses are more in number.
- Steel forms can be installed and dismantled with greater ease and speed.
- The quality of exposed concrete surface by using steel forms is good and such surfaces need no further treatment.
- Steel formwork does not absorb moisture from concrete.
- Steel formwork does not shrink or warp.
Construction of formwork:
This normally involves the following operations:
- Propping and centring
- Shuttering
- Provision of camber
- Cleaning and surface treatment
Order and method of removing formwork:
The sequence of orders and method of removal of formwork are as follows:
- Shuttering forming the vertical faces of walls, beams and column sides should be removed first as they bear no load but only retain the concrete.
- Shuttering forming soffit of slabs should be removed next.
- Shuttering forming soffit of beams, girders or other heavily loaded shuttering should be removed in the end.
Rapid hardening cement, warm weather and light loading conditions allow early removal of formwork. The formwork should under no circumstances be allowed to be removed until all the concrete reaches strength of atleast twice the stresses to which the concrete may be subjected at the time of removal of formwork. All formworks should be eased gradually and carefully in order to prevent the load being suddenly transferred to concrete.
Figure 1 to 6 shows formwork for different types of members in civil engineering construction.

Figure 1(a): Details of timber formwork for RCC beam and slab floor

Figure 1(b): Details at section (A) shown in above figure

Figure 2(a): Elevation

Figure 2(b): Details of timber formwork for circular RCC column

Figure 3(a): 150 3D View

Figure 3(b): Details of timber formwork for square or rectangular RCC column

Figure 4: Sectional plan showing details of timber formwork for an octagonal column

Figure 5: Details of formwork for stair

Figure 6: Timber formwork for RCC wall
Table: Period of removal of formwork
S. No.
| Description of structural member
| Period of time
|
1
| Walls, columns and vertical sides of beams | 1 to 2 days |
2
| Slabs (props left under) | 3 days |
3
| Beam soffits (props left under) | 7 days |
4
| Removal of props to slabs |
|
| (a) For slabs spanning upto 4.5 m | 7 days |
| (b) For slabs spanning over 4.5 m | 14 days |
5
| Removal of props to beams and arches |
|
| (a) Spanning upto 6 m | 14 days |
| (b) spanning over 6 m | 21 days |

steel,wood form work
I would like to learn all types of form work methods and designs kindly provide the information about the new methods & demos to improve my knowledge in my construction proffession.Regards,Rajendra.
Hi Gopal Mishra.I'm Benjamin Kardel from VietNam.I'm interested in Construction field.your blog containt many posting which are interested.May I copy these post and Links to my Blog? Tks you.
My blog at: http://www.construction-site-vn.blogspot.com.
Nice to meet you.
Hi Benjamin,
you can not copy complete post and put in your blog, but you can copy 2-3 lines, like an abstract and post in your blog with a link to the original post on the constructor.
excuse me, to all the civil engineers out there, iam a student conducting a feasibility study, can you please suggest some topic that I can study on our feasibility? thanks. :)
feasibility study of what?
Gopal Mishra we are studying for some civil engineering problems or even some equipments that e are using on the field that we can still innovate. can you please suggest some study that our group can still conduct? thanks.
hello, Arianne Punzalan
the main thing is in the field of construction is CONCRETE TECHNOLOGY.
dear can u innovate leveling machine for slab checking without needing leveling just install it and ready to use
Er Niraj Kumar . Steel is the heart of the construction. so, learn how the steel is designed for the building as per S.B.C.(soil capacity) and give quantities of steel in columns, beams and slabs water tanks and checking .
Arianne – have a look at what moladi does – Reusable plastic formwork http://moladi.blogspot.com
gud 1
cn newe1 plzzzzzz tel me abt a site 4m wer I cn download my projcts………
this site is useful.
Dear Mr.Gopal, I am Rajesh from Sri Raam Traders,Tamil Nadu.I am one of the leading Building Construction MatConterial supplier in my city.And also young growing builder.Basically i have a 3 years experience in Construction field.Last May i was started a New Residance contract work.i have a lot of suggestion in this work.
I wil send my plan to ur mail.so plsend me email id to my mail.i will send all the details to u.
Thanks & Regards,
Rajesh.
thanks for the informations…
there is a lot of new information that I got. thanks alot
Nice article. Specially shutter opening table is very helpfull.
Thank you for this info – maybe you can compile an article on moladi plastic formwork – http://www.moladi.net.
thanks for infomation.
thank you for this information!
Thanks for good article it is very usful.
Attn! Attn! attn! everyone………
we r the manufractures of steel scaffolding & formworks products. we r JVR FORGINGS LTD.Everyone who have required pls contct me. Rishi Singh or rishisingh@jvrforgings.com.
nice job 4 u people.
how to build timber form work.
good
Hi mr. Niraj , If u want 7 days Com. strength for 1:1 1/2:3 ratio , then u required to know about nominal mix design . above ratio gives 20n/sq.mm after 28days and required to achive 67% strength at the age of 7 day.
hello good morning,Vaibhav Jadhav
I know these things ,but what is the minimum & maximum strength required after seven days test?
1:1.5:3 is the nominal mix for M20 concrete. We all know that 7 day strength of a standard cube (as per IS) is 2/3 rd of the 28 day strength. So, in this case the minimum 7 day strength for M20 concrete is 0.67 x 20 = 13.4 MPa. Maximum strength at 7 day is not estimated in field as the only maximum strength desired to be achieved after 28 days is the target characteristic strength. :)