RCC COLUMNS

    Materials and Machinery used

    • Batching plant.

    • Transit mixer

    • Concrete pump

    • Vibrators

    • Chute and C I Pipes.

        Scope

        • Marking the columns

        • Placing the reinforcement

        • Form work for columns

        • Placing the concrete

            Erection of Column

            • The size of column to be marked and checked

            • Form work consists of plywood board / Wall forms with rigid supports by Jacks/tubes.

            • Reinforcement shall be cut and placed as per the structural drawings and approved bar bending Schedules. Specified cover blocks should be provided at regular spacing and intervals. Cover blocks should be tied with reinforcement by using binding wires for preventing misplacement from its location during concreting

                RCC BEAM

                Materials and Machinery Used

                • Batching plant.

                • Transit mixer

                • Concrete pump

                • Vibrators

                • Chute and C I Pipes.

                    Scope of the work

                    • Marking the grade beams

                    • Placing the reinforcement

                    • Form work for grade beams

                    • Placing the concrete

                        Erection of beam

                        • The size of grade beam to be marked and checked

                        • Form work consists of plywood board / Wall forms with rigid supports by Jacks/tubes.

                        • Reinforcement shall be cut and placed as per the structural drawings and approved bar bending Schedules. Specified cover blocks should be provided at regular spacing and intervals. Cover blocks should be tied with reinforcement by using binding wires for preventing misplacement from its location during concreting.

                          Placing of concrete

                          1. Verify the marking, steel reinforcements and formwork and get approvals from clients by using concrete pour cards.

                          2. As the Grade beam to be casted monolithic with column and the grades of the concrete are different, we follow the following procedure.

                          rcc column