Material Estimation

METHODS & UNITS OF MEASUREMENTS OF CIVIL WORKS

The units of measurements (UOM) for civil engineering works are mainly categorised for their nature, shape and size and for making payments to the contractor and also. The principle of units of measurements normally consists the following: a) Single units work like doors, windows, trusses etc., are expressed in numbers. b) Works consists linear measurements […]

UNITS OF MEASUREMENT AND PAYMENT FOR VARIOUS ITEMS

UNITS OF MEASUREMENT AND PAYMENT FOR VARIOUS ITEMS Sl. No. Particulars of items Units of measurement Unit of payment 1 Earthwork: Excavation, filling, cutting, banking m3 100 m3 2 Surface dressing m2 m2 3 Cutting of trees Number Per number 4 Stones: quarrying, blasting m3 m3 5 Concrete : PCC, RCC, Precast m3 m3 6 […]

SIZE AND QUANTITY OF REINFORCEMENT FOR BUILDING WORKS

Reinforcement is required for reinforced concrete members such as footings, beams, columns, slabs, lintels etc. Estimation of reinforcement quantity is required prior to tendering stage to calculate approximate cost of project or construction work. Following table gives the estimated quantities of reinforcement and its size generally used for various building works: Sl. No RCC Member […]

LABOUR REQUIREMENT FOR VARIOUS BUILDING WORKS

LABOUR REQUIREMENT FOR VARIOUS BUILDING WORKS: The table below shows the recommended labour requirement for various civil engineering/building/construction works: S.No. Description of work Unit Labour Recommended constant in days. Remarks 1) Excavation over areas (hard/dense soil),depth up to 1.5m and removal (up to one meter from edge) M3 Mate Labour 0.06 0.62 _ _ 2) […]

ESTIMATION METHODS OF BUILDING WORKS

The estimation of building quantities like earth work, foundation concrete, brickwork in plinth and super structure etc., can be workout by any of following two methods: a) Long wall – short wall method b) Centre line method. c) Partly centre line and short wall method. a) Long wall-short wall method: In this method, the wall […]

MEASUREMENT OF REINFORCED CONCRETE WORKS

Measurement of Reinforced Concrete Works: 1. The Quantities can be rounded off to the nearest two decimals. 2. Concrete in Structural members, such as columns, Beams and slabs shall each be measured separately. 3. No Deductions shall be made for the following Opening up to 0.1 m2 Volume occupied by reinforcement. Volume occupied by pipes, […]

QUANTITIES OF MATERIALS PER CUBIC METRE OF CONCRETE

  ESTIMATED QUANTITIES OF MATERIALS REQUIRED PER CUBIC METRE OF COMPACTED MORTAR OR CONCRETE NOMINAL MIX   WATER CEMENT RATIO   WATER PER 50KG BAG OF CEMENT   CEMENT   SAND (CUM)   CRUSHED STONES (CUM)   CEMENT   F.A.   C.A.   BY WEIGHT (KG)   BY NUMBER OF BAGS   1   1 […]