Methods of Pouring Concrete as per Recommendations of ACI 304R-00

Reading time: 1 minute

Concrete pouring is a crucial process which not only needs properly qualified persons but also considerable focus and concentrations. Almost all codes have established certain specifications to ensure proper concrete pouring and prevent its segregation. In this article, correct concrete pouring according to ACI 304R-00 is presented.

Fig.1: Concrete Pour Placement

Precautions during Concrete Pouring

The ACI 304R-00 has provided several precautions for pouring concrete which include:

ACI Code Recommendation for Concrete Pouring of Different Reinforced Concrete Elements

In this section, suitable method of concrete pouring for various reinforced concrete elements will be discussed. The elements include columns and walls, slabs, inclined slabs, and curved members. If these suitable techniques are applied correctly, then the occurrence of segregation and honeycomb can be prevented.

Pouring of Concrete in Columns and Walls

If the height of these elements is large, then it is recommended to place concrete in layers. The layer thickness ranges from 300mm to 500mm and the time between successive layers should not exceed 30 minutes for normal weather condition and 20 minutes for hot weather condition. Each layer should be compacted properly using vibrators. Figure 2 explains correct (A) and incorrect (B) method of concrete pouring into deep forms in layers. Figure B is not desired since concrete would strike form face and segregation would occur.

Fig.2: Pouring concrete into deep forms in layers, A) Proper way of pouring concrete, B) incorrect method of pouring

When height of forms in not large and concrete poured from the top of the forms, then the ACI code recommends discharging concrete into light hopper and then place concrete into its final location as explained in Figure 3.

Fig.3: Recommended way of pouring concrete into narrow forms

Lastly, if steady concrete pouring is not achieved and concrete strike against the form as explained in Figure 4, the concrete would suffer from separation and hence honeycomb at the bottom would prevail.

Fig.4: Improper pouring of concrete into narrow forms such as walls and columns

Pouring of Concrete in Slabs

The ACI Code recommends placing concrete into face of concrete in place as shown Figure 5 in rather than away from the face of concrete in place as shown in Figure 6.

Fig.5: Pouring concrete into the face of concrete in place as recommends by ACI 304R-00

Fig.6: Incorrect pouring of concrete which should be prevented during slab construction

Pouring of Concrete for Inclined Slabs

Commonly, pouring concrete of inclined surfaces is more challenging compare to horizontal surfaces and hence it needs more efforts to avoid segregation. The ACI 304R-00 recommends the application of baffle and drop at the end of the chute to avoid concrete separation and make sure that concrete stay on the slope. This process is illustrated in Figure 7.

Fig.7: Pouring concrete on slope slab using baffle to prevent concrete separation

However, if such technique is not used, then it is highly possible that concrete would suffer separation and large size aggregates would settle at the bottom as shown in Figure 8.

Fig.8: Improper pouring of concrete, large size aggregates settled at the bottom

Pouring of Concrete for Curved Members

Curved members could be beams, columns, walls, or slabs. The ACI 304R-00 recommends to pour concrete in layers as explained in Figure 9.

Fig.9: A) Correct method of concrete pouring, B) Incorrect method of concrete pouring

Concrete Pouring Using Pumps

Nowadays, pumps are widely used to pour concrete instead of other conventional equipments. It is advised to extend the hose of pumps as close as possible to the final position of concrete to prevent segregation and other undesired effects. Figure 10 and Figure 11 shows the desired way of placing pouring concrete using pumps for both right and curved members respectively.

Fig.10: Extending pump hose near final location of concrete

Fig.11: Extending pump hose close to the final position of concrete