The Constructor

How to Determine Termination Point of Piles in Construction?

How to determine Termination Level of Pile in Construction Site

Reading time: 1 minute

Deciding on the termination point of piles during the construction process is a critical task. The actual pile termination level may increase or decrease and is finalized during the execution of the drilling process.

Pile penetration ratio and chisel energy level are two methods that are used to decide the termination depth of a pile. Through these methods, an optimized length can be specified for the pile under consideration. Hence, these two methods are used for establishing similarity in soil strata.

What are the Termination Criteria of Pile at Construction Site?

1. Pile Penetration Ratio (PPR) for Rotary Piling

The pile penetration ratio (PPR) is used to ensure that the desired rock layer is reached during the construction process. The actual pile termination point is determined based on the energy requirement of the rotary piling rig for a specified PPR.

The PPR reflects the energy in ton-meter required to advance the pile bore of 1 m2 cross-sectional area by 1 cm, as per IRC: 78-2014. With the use of rotary piling, Ganpule and Gupte modified energy concept to derive the following equation for the determination of pile termination point:

PPR=(2⋅π⋅N⋅T⋅t)/(A⋅d)                           Equation 1

Where:

PPR: Pile penetration ratio, kN m/m2/ cm

N: RPM

T: Torque corresponding to RPM, kN.m

t: Time duration in minutes, normally 10 min

A: Pile cross-section area, m2

D: Pile penetration, cm

As the resistance to rock cutting increases, RPM decreases, and Kelly bar pressure is required to be increased, i.e., increasing the torque. This is reflected in the torque- RPM curve, as shown in Fig. 1 and Fig. 2. Table-1 shows typical PPR observed at a particular construction site.

Piling manufacturers may furnish the torque-RPM curve exclusive for the machine used. Torque meters can be placed on the control panels of hydraulic rigs to measure the torque.

Fig. 1: Typical Torque-RPM diagram of 180 kN m capacity rotary rig
Fig. 2: Typical Torque-RPM Diagram of 130 kN m capacity rotary rig

Table-1: Typical PPR rates for rotary auger piling rig, with Torque 180 kN m and RPM 10

Pile penetration ratio (PPR) (kN m/m2/cm)Type of strataRate of penetration (cm/min)
500-750Soil40-60
750-1500Highly weathered rock20-40
1500-3000Moderately weathered rock10-20
300-6000Slightly weathered breccia5-15

2. Chiseling Energy Concept

Datye and Karandikar established the chiseling energy concept for the termination of pile depth. Use the following expression to estimate the response of founding rock strata in terms of Energy Level:

E=(W⋅h⋅n⋅N)/(A⋅d)                         Equation 2

Where:

E: Chisel energy level, kN.m/m2/cm

W: Weight of chisel, kN

h: Fall of the chisel in meters given in every blow (m)

n: Reduction factor, 0.8–1.0 based on likely drag on chisel due to slurry, submerged weight of chisel in high groundwater, winch rope friction, and type of muck (clayey or sandy), based on rock type.

N: No. of blows in the stipulated duration, usually half an hour

A: Nominal pile cross-sectional area, m2

D: Penetration into the rock strata in that stipulated duration, cm

The chisel energy response data can be plotted depth-wise side by side with the nearby bore log and hours of chiseling, as in Fig. 3. The pile termination zone can be decided to optimize the chiseling effort further while also ensuring the pile capacity.

Fig. 3: Chiseling Energy Concept; Typical Data Sheet

FAQs about pile termination depth in construction site

What are the pile termination point criteria?

There are two equations or methods that can be used to decide the termination level of piles during execution, namely the Pile penetration ratio and chisel energy level.

Why is the determination of pile termination level important?

The actual pile termination level may increase or decrease and is finalized during the execution of the drilling process.

What is pile socket length?

The depth up to which a pile-end needs to be penetrated into sound and rock or soil layer is called pile socket length.

How to determine pile socket length?

Pile socket length is equal to the diameter of the pile times one.

Read more:

How to Pour Concrete for Pile Foundation?

Exit mobile version