Repair of Concrete Columns for Cracks and Damages

Before starting the repair of a concrete column, the axial dead load, axial live load, horizontal load and its associated moments must be known. Repairs to concrete columns can be divided into two categories. Surface or cosmetic repair only covers local deterioration and structural repair restores or strengthens the affected columns. If the deterioration does not significantly reduce the cross section, the conventional concrete repair can successfully be employed. Methods of Concrete Column Repair for Damages and Cracks

Methods of Concrete Column Repair for Damages and Cracks

Columns may be repaired by using one or more of the following methods:

Following parameters are important for the design and the execution of the column repair:

Unloading Columns

In those cases where the column deterioration is significant, unloading the column is usually required so that the entire cross section of the repaired column is capable of carrying the reintroduced design load. Without this unloading, the new repair will hardly carry any load. Drying shrinkage of new material may further reduce this share of load. Unfortunately, it can be difficult and expensive to unload columns, especially in high-rise buildings. If the existing load on a column is not removed before the repair, the jacket will only provide confinement to the existing column. The percentage of direct load taken by jacket will be very small (less than 25 percent of the jacket strength). If it is not possible to remove the load from the column, then a supplemental column system can provide an alternative method of support in combination with the repair of the existing column.

Redistribution of the Load

In case of corrosion of reinforcement and significant concrete deterioration, the load is redistributed in the structure before repair to a new pattern which must be considered while designing the repair. Even the adjoining members may have been affected by this redistribution.

Supplemental Reinforcing Steel

The column ties can not usually be disturbed during the repair as it may cause buckling of the longitudinal bars. Hence, the supplemental vertical bars may be placed outside the original cage with extra ties. When the supplemental bars are placed outside the tie bars, the column dimensions should be increased to provide adequate cover. Hairpin ties, usually of stainless steel, are used to laterally support the supplemental bars.

Concrete Removal

The removal of concrete within a column cage must only be done if the column is unloaded. Otherwise, the longitudinal bars may buckle and compression failure of column may take place.

Corroded Reinforcing Steel

It is not necessary to remove the corroded reinforcing bar with reduced cross-sectional area if the loss is supplemented with additional reinforcing bars. The lap length of such a splice must be provided corresponding to the area lost by corrosion to either side of the corroded portion of the reinforcing bar that is supplemented. The partially corroded reinforcing bars that are left in place must be thoroughly cleaned by sandblasting to obtain bare metal. The bars with excessive corrosion must be replaced with fresh reinforcement having full laps on both sides.

Corroded Ties

The corroded ties can be replaced by adding stainless steel hairpin ties that are anchored into the concrete. It is often necessary to deposit extra material around columns to provide adequate cover over the supplemental ties.

Low-strength Concrete

Where the concrete strength is low, resulting in insufficient load-carrying capacity, several alternatives are available: