The area where i am supervising was sloped and we had to cut at upper slope and fill at the lower slope in order to make a leveled area. during the excavation of trenches the trenches at the filled area ...
Reinforcements used in the process of prestressing: Especially in case of prestressing, we are using strands of Steel and it's called tendons. Tendons are made of high strength Steel. Three major types of reinforcements which are used in Prestressing: Spalling R/f Equilibrium R/f Bursting R/f CombinRead more
Reinforcements used in the process of prestressing:
Especially in case of prestressing, we are using strands of Steel and it’s called tendons.
Tendons are made of high strength Steel.
Three major types of reinforcements which are used in Prestressing:
- Spalling R/f
- Equilibrium R/f
- Bursting R/f
Combination of reducing the structural thickness reduced conventional reinforcements quantities and fast construction often results in un prestressed structure.
Thank You. Â
See less

Pranta Narula
My plot of land is low lying and needs to be earth filled for approximately 1 to 1.5 metre. Now my question is that Can i start foundation of a 2 storey building on the ground without excavation ? after that we can filled the rest of the plot with earth.
My plot of land is low lying and needs to be earth filled for approximately 1 to 1.5 metre. Now my question is that Can i start foundation of a 2 storey building on the ground without excavation ? after that we can filled the rest of the plot with earth.