What is the mobilization & demobilization cost of any project, in percentage?
Bituminous Macadam is a Binder which is used for the 24-meter & 12-meter roads where the traffic movement is heavy. This can be laid in two or more courses for the better compressive strength. This shall comprise of 5 TO 7 percentage of bitumen. Semi Dense Bituminous Macadam is a binder that isRead more
Bituminous Macadam is a Binder which is used for the 24-meter & 12-meter roads where the traffic movement is heavy. This can be laid in two or more courses for the better compressive strength. This shall comprise of 5 TO 7 percentage of bitumen.
Semi Dense Bituminous Macadam is a binder that is laid after the BM course to obtain smoother finish on road surfaces. This is used in small roads of width less than 9 Meters. This course is laid directly on the wet mix macadam in smaller roads with a thickness of 25-30 mm. This shall comprise of 3 to 5 percentage of Bitumen.
See less
Soumyadeep Halder
Mobilization and demobilization costs can vary greatly depending on the type of work being performed and what level of costs and logistics will be required to get the job rolling. So, there isn’t really one rule of thumb to follow on all projects. But, mobilization should represent the actual costsRead more
Mobilization and demobilization costs can vary greatly depending on the type of work being performed and what level of costs and logistics will be required to get the job rolling. So, there isn’t really one rule of thumb to follow on all projects.
But, mobilization should represent the actual costs of accumulating and coordinating all the necessary equipment, tools, materials, etc. – it shouldn’t typically be made up independently and without a sound basis. With that being said, mobilization costs tend to be under 10% and even as low as 2%. And as mentioned above, that should be pretty tightly tied to the actual costs of mobilizing and demobilizing the job.