Sign Up

Sign Up to The Constructor to ask questions, answer people’s questions, write articles, and connect with other people. VIP members get additional benefits.

Sign In

Login to The Constructor to ask questions, answer people’s questions, write articles & connect with other people. VIP members get additional benefits.

Forgot Password

Lost your password? Please enter your email address. You will receive a link and will create a new password via email.

Sorry, you do not have permission to ask a question, You must login to ask question. Become VIP Member

Get More Features, Sign Up Now. Become VIP Member

Print, PDF & Email

A building is set out in order to clearly define the outline of the excavation and the centre line of the walls, so that construction can be carried out exactly according to the plan. The centre line method of setting out is generally preferred and adopted.

Procedure for Setting Out a Building Plan on Ground

SETTING OUT A BUILDING PLAN ON GROUND

Fig.1: Example plan to be set out on the ground

1. From the plan (fig 1), the centre line of the walls are calculated. Then the centre lines of the rooms are set out by setting perpendiculars in the ratio 3:4:5. Suppose the corner points are a, b, c, d, e, f and g which are marked by pegs with nails on top.

2. The setting of the corner point is checked according to diagonals ac, bd, cf and eg.

3. During excavation, the centre points a, b, c, d, e, f, g may be removed. Therefore the centre lines are extended and the centre points are marked about 2m away from the outer edge of excavation.

Thus the points A1, A2, B1, B2 and likewise, are marked outside the trench. Centre line are shown clearly by stretching thread or rope. The centre points fixed 2m away from the excavation are marked with sit out pegs.

4. From the plan details, the width of excavation to be done is also marked by thread with pegs at appropriate positions.

5. The excavation width is then marked by lime or by with furrow with spade.

6. If the plan is much to complicated and follows a zigzag pattern, then the centre pegs are kept at suitable positions according to site conditions.

Sign up to email updates and Get Free Ebook on Concrete Repair Methods, Techniques and Guidelines.

Gopal Mishra

Gopal Mishra

Gopal Mishra is a Civil Engineer from NIT Calicut and has more than 10 years of experience in Civil Engineering and Construction. He is the founder of The Constructor.

Related Articles

26 Comments

  1. keep in mind that the string also needs to be in level otherwise we will have the hypotenuse problem especially for longer lengths.

Leave a comment

You must login to add a new comment.